REVISED SCHEDULE AS OF 2/6/09
Canal 19 (complete)
Canal 18 (complete)
Canal 7 (complete)
Canal 8 (complete)
Canal 9 (complete)
Canal 10 (complete)
Canal 11 (complete)
Canal 12 (complete)
Canal 6 Feb. 5 - 10th (east side of Dare, west side of Pender)
Canal 5 Feb. 11 - 16 (east side of Pender, west side of Leland)
No dredging while Booster Pump is installed: February 17
Canal 12 Feb. 18- 23 (west side of Scotland, east side of Richmond)
Canal 13 Feb. 24- March 1 (west side of Richmond, east side of Concord)
Canal 4 March 2- 7 (east side of Leland, west side of Moore)
Canal 3 March 8 - 13 (east side of Moore, west side of Cumberland)
Canal 2 March 14 - 19 (east side of Cumberland, west side of Goldsboro)
Canal 1 March 20 - 25 (east side of Goldsboro, west side of Lee)
Diane Dalen
Broker-In-Charge
Ocean Isle Beach
REVISED SCHEDULE AS OF 2/6/09
Canal 19 (complete)
Canal 18 (complete)
Canal 7 (complete)
Canal 8 (complete)
Canal 9 (complete)
Canal 10 (complete)
Canal 11 (complete)
Canal 12 (complete)
Canal 6 Feb. 5 - 10th (east side of Dare, west side of Pender)
Canal 5 Feb. 11 - 16 (east side of Pender, west side of Leland)
No dredging while Booster Pump is installed: February 17
Canal 12 Feb. 18- 23 (west side of Scotland, east side of Richmond)
Canal 13 Feb. 24- March 1 (west side of Richmond, east side of Concord)
Canal 4 March 2- 7 (east side of Leland, west side of Moore)
Canal 3 March 8 - 13 (east side of Moore, west side of Cumberland)
Canal 2 March 14 - 19 (east side of Cumberland, west side of Goldsboro)
Canal 1 March 20 - 25 (east side of Goldsboro, west side of Lee)