2008-2009 Concrete Dredging Schedule


Just wanted to let the concrete canal home owners of Ocean Isle Beach know of the dreding schedule published by townsip- Hope it helps!

REVISED SCHEDULE AS OF 2/6/09

Canal 19 (complete)

Canal 18 (complete)

Canal 7 (complete)

Canal 8 (complete)

Canal 9 (complete)

Canal 10 (complete)

Canal 11 (complete)

Canal 12 (complete)

Canal 6 Feb. 5 - 10th (east side of Dare, west side of Pender)

Canal 5 Feb. 11 - 16 (east side of Pender, west side of Leland)

No dredging while Booster Pump is installed: February 17

Canal 12 Feb. 18- 23 (west side of Scotland, east side of Richmond)

Canal 13 Feb. 24- March 1 (west side of Richmond, east side of Concord)

Canal 4 March 2- 7 (east side of Leland, west side of Moore)

Canal 3 March 8 - 13 (east side of Moore, west side of Cumberland)

Canal 2 March 14 - 19 (east side of Cumberland, west side of Goldsboro)

Canal 1 March 20 - 25 (east side of Goldsboro, west side of Lee)

Diane Dalen